About the EIS

EnergyCo has prepared an environmental impact statement (EIS) for the New England Renewable Energy Zone (REZ) Network Infrastructure Project. The EIS explains  the proposed project, potential impacts on the environment, communities and landholders, and measures to avoid, minimise and manage impacts. 

The EIS is now on public exhibition for 28 days until the 12 November, giving community members and stakeholders the opportunity to review the project and make a submission to the NSW Department of Planning, Housing and Infrastructure (DPHI). 

How to make a submission?

DPHI requires submissions to be made online using the NSW Planning Portal. If you need help accessing the portal online, please get in touch with our team or visit an information session. 

Visit the NSW Planning Portal and make a submission

 

Before making your submission, please read DPHI’s Privacy Statement at planning.nsw.gov.au/privacy or phone 1300 305 695 for a copy. DPHI will publish your submission on its website in accordance with their Privacy Statement.

new-england-rez-20240327-_EnergyCo_MuswellbrookCES_TZ-6906_edited

Project timeline

  1. Start the planning and approval process

    We lodged the project’s scoping report in July 2024. In September 2024, the Secretary’s Environmental Assessment Requirements (SEARs) were issued.

  2. Prepare the environmental impact statement

    We carried out technical assessments of the projects impacts and opportunities and consulting with the community on potential impacts.

  3. Public exhibition of the environmental impact statement

    The EIS for the New England REZ Network Infrastructure Project will be on public exhibition from 15 October for at least 28 days. The exhibition period is determined by the DPHI, which will also decide whether any extension to the exhibition period is required.

  4. Submissions Report

    Once the public exhibition period has closed, DPHI will collate all submissions and provide them to EnergyCo for review and consideration. EnergyCo will then prepare a submissions report responding to the issues raised. The submissions report will be made publicly available on the NSW Planning Portal and on this page.

    If the project is approved, it would be built and operated in accordance with the plans and mitigation measures outlined in the EIS, as well as any conditions of approval.

Opportunities to learn more

To learn more and get involved in the EIS exhibition, view our schedule of upcoming engagement events:

""

Community roadshow

Location DateTimeVenue
WalchaTuesday 27 October12-3pmWalcha Vet Supplies
KentuckyWednesday 28 October3-6pmKentucky Memorial Hall 
GundyMonday 2 November3-6pmSoldiers’ Memorial Hall
RouchelWednesday 4 November3-6pmRouchel School of Arts Hall 
SconeThursday 5 November3-6pmScone Motor Inn Conference Centre 
MuswellbrookFriday 6 November11am-2pmMuswellbrook Library Seminar Room 
WalchaMonday 9 November4-6pmWalcha Central School Hall 
UrallaTuesday 10 November3-6pmUralla Courthouse 
ArmidaleWednesday 11 November3-6pmArmidale Town Hall 
TamworthThursday 12 November12-2pmTamworth Community Event Centre 
""

Webinars

TopicDateTimeRegistration
Understanding the EISTuesday, 20 October4pm - 5pmRegister now
How we build the REZThursday. 22 October4pm - 5pmRegister now
Landholder Q&A sessionMonday, 26 October 4pm - 5pmRegister now
Managing biodiversity and environmental impactsTuesday, 3 November4pm - 5pmRegister now

What happens after EIS consultation?

Once the exhibition period closes, all submissions will be reviewed as part of the planning assessment process. EnergyCo will prepare a Submissions Report that responds to the issues and feedback raised by community members, landholders, councils, government agencies and other stakeholders.

The Submissions Report will be published and considered alongside the EIS by the Minister for Planning and Public Spaces when making a decision on the project.

If the project is approved, it will be delivered in accordance with the commitments outlined in the EIS and any conditions of approval.

As planning and design continue, there may be opportunities to refine aspects of the project, including elements of the design, construction methods and environmental management measures. These refinements will be informed by community feedback, ongoing technical investigations and detailed planning by the future network operator.

As a result, some project details may change before construction begins. Any changes will be assessed to ensure they remain consistent with the impacts assessed in the EIS and comply with planning approval requirements. Where additional approvals are needed, the relevant planning processes will be followed, including opportunities for community input where required.

new-england-rez-20240325-_EnergyCo_ArmidaleCES_TZ-6486

Frequently asked questions

How will EnergyCo manage the impacts of the project on native vegetation and local flora and fauna species?

We understand that our local communities care about their surrounding environments including native vegetation. We are committed to reducing the project’s impact by carefully planning our work and protecting local species and landscapes.
Less than a third of the project footprint involves native vegetation removal – around 3,203 hectares. Of the native vegetation to be removed, around 42 per cent is forest and woodland while the rest is grassland.

In all instances we will seek to avoid and minimise environmental impacts where possible, and the project will have no impact on national parks or nature reserves. 
Where impacts cannot be avoided, they will be managed in accordance with NSW’s biodiversity assessment and offset requirements.

How will environmental impacts be offset?

When an infrastructure project impacts native plants, animals or habitats, NSW legislation requires these impacts to be offset by gains that benefit those same species and ecosystems.

This means conserving and enhancing biodiversity in other locations so that, overall, there is no net loss.

EnergyCo will meet its biodiversity offset obligations for the project through a strategic offset delivery agreement (SODA) with the NSW Department of Climate Change, Energy, the Environment and Water (DCCEEW).

Under the SODA, it’s expected that at least 4,000 hectares of koala habitat would be protected and restored. This will help protect land that provides food, shelter and movement corridors for koalas, helping to strengthen habitat connectivity and improve resilience of local koala populations over time.

How will EnergyCo manage impacts on koalas and other wildlife?

We recognise the strong community connection to koalas and the importance of protecting koalas and other wildlife.

The EIS identifies that around 1,373 hectares of koala habitat would be impacted by the project. Of this, 604 hectares is forest and woodland while 768 hectares is scattered trees, mostly in farmland.

Impacts on koala habitat will be offset, and we expect to see an extensive area of habitat restoration delivered.

We are looking at ways to ensure animals, including koalas, move across the transmission corridor safely. This may include retaining trees in some places, providing koala refuge poles, glider poles, rope bridges and keeping important habitat features like hollow logs and rocks on the ground for smaller animals.

We are working to keep smaller trees and vegetation where we can in the transmission easement.

A connectivity strategy will be prepared that identifies where habitat linkages are, and how we will encourage animals to continue to move through the transmission easement to those habitat linkages.

What workforce accommodation is planned for the project?

To build the infrastructure required for the New England REZ we will require a large workforce that will be spread across five proposed workforce camps of around 320 to 550 beds each. The workforce will include around 1,400 people at peak.

The proposed locations of the workforce camps are close to where we are planning construction, meaning less travel time for workers and reduced impacts on local traffic.   

Providing dedicated accommodation and facilities will help reduce pressure on local housing and short-term accommodation while supporting safe and efficient construction.

Will there be local job opportunities on the project?

Construction of the New England REZ network infrastructure project will require a large workforce.

EnergyCo and its future network operator will focus on maximising opportunities for local workers, businesses and suppliers through employment pathways, training and regional procurement opportunities. 

The project is expected to create around 1,000 jobs in the New England region and around 2,000 direct and indirect construction jobs in NSW.

While some specialised roles will need to be filled by workers from outside the region, EnergyCo and the network operator will work to maximise local participation wherever possible.

Will there be impacts on farming and agricultural production in the region?

EnergyCo understands the vital role farming and agriculture play in the New England and Upper Hunter regions. 

Agriculture and transmission lines successfully co‑exist across NSW. Farmers routinely run grazing, cropping and day‑to‑day farm operations under and around transmission lines. This is standard practice across the state’s existing 330 kV and 500 kV networks.

The total reduction in agricultural production value during construction is minor, equating to approximately 0.1% of total agricultural output across affected local government areas. 

Once the project is operational, the impact to agricultural output decreases to an annual production loss of around 0.02%. 

The project’s 471‑hectare operational footprint includes 438 hectares of agricultural land, representing a minor impact at a regional scale. 

Most farming activities can continue safely in and around the easement once operational.

How will anthrax and biosecurity risks be managed?

EnergyCo recognises the biosecurity concerns for farmers, and we have been working with the Department of Primary Industries and Regional Development (DPIRD) and anthrax specialists to assess and manage any impacts. 

Anthrax spores occur naturally in some soils in parts of Australia. Some transmission infrastructure for the New England REZ is proposed in the Rouchel area in the Upper Hunter region where historical anthrax outbreaks have been recorded.

Biosecurity controls will be outlined in a biosecurity management plan which will be implemented during construction to minimise the risk of the spread of disease, pests or weeds. 

We will also implement the animal biosecurity management procedures for anthrax outlined by DPIRD. We will work with landholders to develop property‑specific risk‑management strategies tailored to their livestock and operations.

How will impacts on local roads and transporting of materials be managed during construction?

The EIS includes a detailed assessment of traffic and transport impacts and identifies measures to manage them safely during construction.

While some temporary traffic changes will be required, including speed reductions, signage and line marking, the project also involves upgrades to parts of the local and state road network, such as turning lanes, road widening and improved access points.

EnergyCo is also working with Transport for NSW on targeted road upgrades to support the safe transport of large renewable energy infrastructure into Renewable Energy Zones.

Will there be impacts from helicopters during construction?

EnergyCo understands that the impacts from noise and vibration is important to our communities, as we've learnt from previous helicopter work in the area. 

Helicopters may be used for conductor stringing, tower erection, aerial inspections and construction support activities. Helicopters may also be used for tower erection in select locations where access is constrained. 

Helicopter activities would generally be short-term and intermittent. Noise impacts are expected to be limited in duration but may be noticeable while helicopter operations are taking place.

We will continue to work closely with landholders to understand potential impacts and listen to feedback to minimise impacts on farms and livestock during any aerial activity.

Will the new transmission lines and energy infrastructure impact the ability to fight fires?

The EIS studies found the presence of new transmission infrastructure would not increase bushfire risk for the community. Transmission lines and energy hubs are being carefully planned to ensure they can operate safely in a bushfire-prone landscape.

We consulted with the NSW Rural Fire Service and firefighting stakeholders as we developed the EIS and will keep working with them as the project progresses.

The transmission corridor was realigned to minimise aerial firefighting impacts at Chaffey Dam and Lake Glenbawn, ensuring water-scooping activities can continue safely. 

Site‑specific bushfire management procedures will be in place during construction and operation to reduce the likelihood of bushfire affecting project infrastructure, ensure safe access for emergency services, and support the continued safe operation of these facilities during bushfire conditions.

NSW Rural Fire Service has established protocols for fighting fires around transmission lines, both from the ground and in the air. 

Will construction of the project impact local water security?

EnergyCo understands water security and avoiding impacts on local water supply are serious issues for communities and councils in the region.

The EIS studies found the project’s water demand would generally be distributed across multiple catchments and water sharing plan areas, representing only a small proportion of available water resources.

Our priority is to capture and store rainwater and reuse treated wastewater where possible. We would then look at entering into agreements with willing landholders, before considering surface and groundwater sources. 

With these measures in place, we expect our water needs to be modest and mostly accessible from existing sources.

What are the opportunities for community and landholders to learn more?

We understand the EIS is a lengthy and technical document and have provided opportunities, tools and resources to help the community better understand its contents. 

EnergyCo will run a range of consultation activities for the EIS, including 10 drop-in information sessions and webinars on key topics.

Drop‑in sessions give people the chance to have detailed conversations with our subject matter experts. Online briefings and webinars also allow community members to ask questions anonymously, which we have heard is important for some people.

Details of upcoming events and all our latest resources will be available on the project’s engagement portal – energyco.nsw.gov.au/nerez

For a comprehensive list of frequently asked questions about the New England REZ, please visit our frequently asked questions.

Useful resources

The full EIS, including all technical reports and appendices, is available on the New England REZ Engagement Portal.

You can also access a range of supporting materials, including fact sheets and project information, designed to help you navigate the EIS and understand the project's potential impacts and benefits.

For assistance, please contact our team or visit one of our information sessions.

Contact the New England REZ team

Call us

Phone 1800 061 114 (toll free), Monday to Friday, 9am to 5 pm

Email us

Send us an email at: nerez@energyco.nsw.gov.au

Learn more, see upcoming events and provide feedback

Register for updates

Sign up for the New England REZ e-newsletter

Get in touch with EnergyCo

Email us
Phone us

Call 1800 118 894 (9am to 5pm, Monday to Friday).

Sign up for our Powering NSW e-newsletter.